Amegni Renewables Ltd Helping Amegni move Carno III towards construction

Carno Wind Farm Wales

The project 

Carno III is the third phase of Carno Wind Farm in Powys, developed by Amegni, the locally based operator of Carno I and II. Located predominantly on forestry land south-west of the existing turbines, its original consent allowed up to 13 turbines, 126.5 m to tip with indicative 41.6 MW of capacity. A subsequent Section 73 approval enabled 13 larger, more efficient turbines with tip heights of up to 149.9 metres and alternative off-site access route.  

Natural Power has supported Amegni since 2008, from feasibility through environmental assessment and consenting, to pre-construction support work. Our integrated planning, environmental and engineering support has helped the client adapt the design to complex site conditions, secure consent for modifications and progress pre-construction requirements.  

 

The client’s challenge 

Amegni needed to adapt its consented wind farm due to changing turbine market conditions and commercial considerations whilst balancing complex ground conditions, peatland and watercourses, and landscape ad visual constraints.  

 

How we responded 

  • Developing a design that responds to site conditions and increased turbine heights. Consented further modifications in 2025 via separate applications to Powys County Council that enabled layout refinements, access improvements and construction infrastructure extensions to optimise design while maintaining environmental compliance.  

  • Providing an assessment that focused on the issues that mattered. Agreement with Powys County Council secured a proportionate environmental assessment scope centred on hydrology, geology and hydrogeology.  

  • Progressing towards construction readiness. Pre-commencement of development conditions are being discharged, with continued support for compliance and monitoring requirements.  

We brought together planning, environmental and engineering expertise, combining site investigations, design refinements and regulator consultation. Our support has continued from feasibility in 2008 through consenting and into the current Owner’s Engineer role.  

 


Client Feedback

"We are delighted to have been working with Natural Power on Carno 3 over the years and value their support in helping us realise the project through the planning phase and now into construction.  Natural Power has planning, environmental and engineering expertise all under one roof which is tremendously beneficial when dealing with complex projects."
 

Sion Thomas, Director, Amegni Renewables Ltd